Bayanix Ltd nearing completion of fit-out works at prestigious complex

Bayanix was appointed by Fiona Barratt Interiors to complete the fit-out works at the newly constructed Chelsea Barracks apartment complex.

The client required lighting, electrical, flooring and decoration work to be carried out before they occupy the multimillion pound apartment in Mulberry Square.

The 5 week project includes:

  • New timber flooring
  • Joinery, including bespoke wall panelling
  • New lighting controls
  • Reconfiguration of electrical power and lighting
  • Installation of ornate decorative lighting
  • Decorations throughout the apartment